Next the Cooler shell arrived. It came on friday afternoon, was moved into position then was left hanging out of the building for the weekend, surely was a topic of conversation for people passing by

1999-4-CUYorkChlrDeliv3Clr.jpg


1999-4-CUYorkChlrDeliv4Clr.jpg


Then on Monday morning the riggers were back to work, the upper Condenser shell was delivered and attached to the Cooler, then slowly and carefully the monstrousity was inched into the building.

1999-4-CUYorkChlrDeliv5ClrCndRig.jpg